Construction Updates for the week of September 7-11
1-26 Concrete Street Paving Project
Week of September 7th
- Pave 2nd sides of Eden, Sullivan and Hendricks & Brill C&G (T)
- Pave 2nd sides of Setter Drive, Bens Way and Boxer Street (W)
Week of September 14th
- Highway-Backfill and Cut walk on Fine Grades (M-TH)
- VCC Grading-Prep sidewalks and driveways (TH-F)
- Martell-Begin sidewalk Late
- Landscaping along Ninth Street will take place later this week.
3-26 Alley Paving Project
- The Seventh/Eighth Alley and the Dixon/Seventh Alley are complete. The landscape contractor will be doing some touch ups to the landscape restoration.
- If grass was planted along the alley behind your property, we ask that you water it when there is no rain.
- The contractor plans to start work on the Fourth/Fifth alley the week of September 7th . They will start removing the existing pavement, excavation, and placing stone in these alleys.
- The contractor may be removing and replacing the alley apron on the Thirteenth/Fourteenth alley at the Main Avenue the week of September 21st.
General Notes
DRIVEWAYS/PARKING – Please do not park on the road while the contractor is performing their work in the area. They need plenty of room for their trucks and equipment to be able to easily, quickly, and safely complete their work. Park in your driveway if possible, or on the nearest side street.
- If you need special accommodations for parking, please reach out as we can arrange different parking options. This includes anyone with disabilities, recent surgeries, expecting mothers, and mothers with newborns that have appointments. Unfortunately, there is no “one size fits all” for parking and property access. The fewer cars that the contractor has to work around, the faster they can get the work done on your block and move on.
WORK ZONE SAFETY – While driving through the construction site, be sure to travel slowly and keep an eye out for equipment. This not only cuts down on dust, but also keeps the construction workers safe. Operators try their best to see traffic, but their view can be obstructed at times. It is always best to try and gain eye contact with equipment operators prior to driving by. You may need to wait at times before driving by depending on the work being performed. Please be patient during construction.
* PLEASE NOTE THAT THIS WORK AND SCHEDULE CAN CHANGE DUE TO WEATHER OR UNFORSEEN CONSTRUCTION DELAYS. THESE UPDATES ARE TO AID THE COMMUNICATION PROCESS AS WE ALL WORK TOGETHER TO COMPLETE THIS PROJECT IN A TIMELY MANNER *
Utility and Street Construction is not easy. There will be dirt, mud, dust, equipment, and workers everywhere. Construction activity will be noisy, and getting to your residence will be difficult at times. We understand that it can be frustrating while it happens, but we ask for your patience and understanding as we make the much needed improvements to your street and utilities. Please do not hesitate to contact our Engineering Department with any questions or concerns. We can’t help if we don’t know.