Construction Updates for the week of July 13-17
1-26 Concrete Street Paving Project
Monday, July 13 starting at 5:00 PM, the sewer lining contractor will be lining the large storm sewer in Hendricks Avenue, from the alley north of Ninth Street to Tenth Street. The sewer lining contractor will be working Monday and Tuesday nights, when it is cooler. The heat that is forecasted for next week causes the resin in the sewer liner to set up quicker, making it harder to do the sewer lining. The noisier work should be done by 9:00 PM, after that it would be the sewer lining crew just doing routine pressure and temperature checks of the water or steam in the new sewer liner. Hot water or steam at pressure is used to push the liner against the existing sewer walls and to cure and harden the resin in the liner.
Week of July 13th
- VCC Grading -Continue grading out 9th street complex (M-F)
- Highway-Begin Backfill & Restore Washington & Florence (M-T)
- Line storm sewer in Hendricks Avenue (M-T)
Week of July 20th
- VCC Grading -Complete grading out 9th street complex (M-F)
General Notes
DRIVEWAYS/PARKING – Please do not park on the road while the contractor is performing their work in the area. They need plenty of room for their trucks and equipment to be able to easily, quickly, and safely complete their work. Park in your driveway if possible, or on the nearest side street.
- If you need special accommodations for parking, please reach out as we can arrange different parking options. This includes anyone with disabilities, recent surgeries, expecting mothers, and mothers with newborns that have appointments. Unfortunately, there is no “one size fits all” for parking and property access. The fewer cars that the contractor has to work around, the faster they can get the work done on your block and move on.
WORK ZONE SAFETY – While driving through the construction site, be sure to travel slowly and keep an eye out for equipment. This not only cuts down on dust, but also keeps the construction workers safe. Operators try their best to see traffic, but their view can be obstructed at times. It is always best to try and gain eye contact with equipment operators prior to driving by. You may need to wait at times before driving by depending on the work being performed. Please be patient during construction.
* PLEASE NOTE THAT THIS WORK AND SCHEDULE CAN CHANGE DUE TO WEATHER OR UNFORSEEN CONSTRUCTION DELAYS. THESE UPDATES ARE TO AID THE COMMUNICATION PROCESS AS WE ALL WORK TOGETHER TO COMPLETE THIS PROJECT IN A TIMELY MANNER *
Utility and Street Construction is not easy. There will be dirt, mud, dust, equipment, and workers everywhere. Construction activity will be noisy, and getting to your residence will be difficult at times. We understand that it can be frustrating while it happens, but we ask for your patience and understanding as we make the much needed improvements to your street and utilities. Please do not hesitate to contact our Engineering Department with any questions or concerns. We can’t help if we don’t know.